We’ve just begun a whirlwind job.

This week we broke ground on Marathon Ranch, where we will be installing Water, Storm, Pumps, Manholes, and roadway improvements that include turnout structures and headwalls. We will also be lining the canal with shotcrete. Roosevelt Water Conservation District (RWCD) has asked us to complete the northern half in just 8 short days.

We’re always up for a challenge! Thank you for trusting us with this opportunity, RWCD.

UPDATE (6/24/17): Our amazing employees worked overtime, double shifts, and weekends to meet RWCD’s needs. We have completed the northern portion and are looking forward to resuming work on the southern half in December. Thanks to our amazing vendors–Rain for Rent, Buesing, and DEG Construction–for your help. We couldn’t have done this without you.